Preliminary Assessment
Planning Permit Application
Soil Tests
Produce Engineering & Construction Drawings
Council Asset Protection Permit
Warranty Insurance
VBA Permit Levy
Building Permit
Inspection of Base/ Stumps
Inspection of framework- prior to lining
Inspection at completion of work- prior to occupation
Certificate of Final Inspection
(L8500mm x W3500mm x h3230/3080)
Front wall 600mm Eave
All timber frame wall and roofing construction
Framing 90mm x 45mm MGP 10
Rafters 140mm x 45mm MGP 10
Includes
Separating wall
Cavity sliding door from main room to bathroom
H2100mm x w1800mm
Double glazed to code As 1288
Selected standard Colorbond finish
H600mm x w1210mm
H1200mm x 1450mm
Double Glazing As 1288
Monument colour finish
Double glazed As 1288
Pre primed reveals Flyscreen included
Front wall and eave cladding material options
Weathertex
Axon sheet
Shadow clad ply
Spotted Gum Shiplap Timber, pre oiled
Grandis H3 treated
Side and rear walls
Colorbond corrugated
Weathertex
Axon sheet
Shadow clad ply
Spotted Gum Shiplap Timber, pre oiled
Grandis H3 treated
Roofing
Colorbond five rib finish
Colorbond guttering and downpipe positioned (no connection)
All flashings finished in required colorbond colour
Gyprock 10mm internal lining
Square set cornices finish
66mm MDF bevelled architraves and skirting pre primed
Hybrid Floorboards
Spotted gum finish (Standard)
Selection range available subject to availability
Rustic Brown
Rustic Rock
Coastal Blackbutt
Qld Spotted Gum
Walnut
Grey Oak
1500mm x 228mm x 7.5mm
200PFC Galvanised Steel Bearers
190/45 LvL Joists
Ezi Piers 90mm set on concrete/450mm diameter/ 800mm deep holes
Expol 60mm Polystyrene floor insulated R-1.4
5 x double power points
5 x internal down lights
2 x external down lights
1 x smoke alarms
IXL Tastic for bathroom Ceiling Fan
Integral Light & mirror to be supplied by client ( ComfyPod to install)
Mitsubishi 2.5 KW Split System
Switchboard/JBox installed
Walls
Hardie weather wrap lined
Pink Batts Soundbreak Insulation R2.7
Roofing
Sisaltion paper lined
Knauf Space blanket 75mm r 1.8 insulated
Flooring Base
Expol 60mm Polystyrene floor insulated R-1.4
Supply & Install
Shower
Basin
Tapware
Toilet as per supplied specifications
Cavity sliding door
Exhaust fan & light
Small hot water service
Waterproofing of wet areas
Plumbing fit off
Hybrid waterproof flooring in required finish
To be determined for underground or aerial connection
Future maintenance
Downpipe connection to storm water or other options.......